Residential Fee Structure
Residential Building Permit Fee Schedule
RESIDENTIAL FEE STRUCTURE
Effective April 1, 2004 |
| |
| The following formula will be utilized in the establishment of the construction costs for residential building permits: |
| |
|
|
|
| Living Space (Outside dimensions) |
$45 per sq. ft. |
|
| |
|
|
|
| Basements (Unfinished) |
$12 per sq. ft. |
|
| |
|
|
|
| Garages (attached) |
$10 per sq. ft. |
|
| |
|
|
|
| Garages (Detached) |
$15 per sq. ft. |
|
| |
|
|
|
| Finished Basement |
$22 sq. ft. |
|
| |
|
|
|
| Sidewalk-Apron Inspection Fee |
$30 |
|
| |
|
|
|
| Decks & Storage Sheds |
$30 |
up to 200 sq. ft. $5 for each additional 100 sq. ft. or fraction thereof |
| |
|
|
|
| Above Ground Pools |
$20 |
|
| |
|
|
|
| In ground Pools |
$100 |
|
| |
|
|
|
| Pole Barns |
$40 |
up to 1,000 sq. ft. $5 for each additional 500 sq. ft. or fraction thereof |
| |
|
|
|
| Demolition |
|
$75 |
|
| |
|
|
|
| Plan Revision Fee |
$50 |
|
| |
|
|
|
| Re inspection Fee |
$50 |
paid prior to the re-inspection |
| Re-inspection fees will be charged as required by the Chief Building Official. |
| |
|
|
|
| Alteration and Repair Fee |
$20 |
per sq. ft. (minimum $50 fee) |
| |
|
|
|
| Construction Start Without Permit |
Double Fee |
|
| |
|
|
|
If the cost of construction submitted by the builder on the permit application is greater than this fee schedule, fees will be based on the construction costs noted on the application.
**Any project started before obtaining a permit shall be charged double per Boone County Ordinance 930.9, Section VI.** |
| |
|
|
|
RESIDENTIAL BUILDING PERMIT FEE SCHEDULE
Effective April 1, 2004 |
| Estimated Construction Cost (Dollars) |
|
Permit Fee |
|
|
|
0 |
- |
999.99 |
20. |
1,000.00 |
- |
4,999.99 |
30. |
5,000.00 |
- |
9,999.99 |
40. |
10,000.00 |
- |
14,999.99 |
60. |
15,000.00 |
- |
29,999.99 |
85. |
30,000.00 |
- |
49,999.99 |
150. |
50,000.00 |
- |
74,999.99 |
200. |
75,000.00 |
- |
99,999.99 |
250. |
100,000.00 |
- |
149,999.99 |
300. |
150,000.00 |
- |
199,999.99 |
400. |
200,000.00 |
- |
249,999.99 |
500. |
250,000.00 |
- |
349,999.99 |
600. |
350,000.00 |
- |
499,999.99 |
800. |
500,000.00 |
- |
749,999.99 |
1,000. |
750,000.00 |
- |
999,999.99 |
1,500. |
| 1,000,000.00 |
- |
1,999,999.99 |
2,500. |
| 2,000,000.00 |
- |
2,999,999.99 |
3,500. |
| 3,000,000.00 |
- |
3,999,999.99 |
4,500. |
| 4,000,000.00 |
- |
4,999,999.99 |
5,500. |
| 5,000,000.00 |
- |
5,999,999.99 |
6,500. |
| |
|
|
|
$1,000.00 for each additional million dollars of construction |
|